Norfork Dam

Lead Contractor on Draft Tube Crane Rehabilitation

Project Details

Completion Date

December 2016

Location

Little Rock, Arkansas

Services Provided

Government Projects

Owner

USACE, Little Rock District

Draft Tube Crane Rehabilitation

  • Demolished the existing 10-ton draft tube gantry crane
  • Manufactured and installed a new 10-ton monorail crane and monorail structure
  • Provided a new power feed, new electrical festoon system, and a new lifting beam
  • Removed and replaced fencing
  • Demolished and reconstructed concrete slab.
  • Lead paint abatement, asbestos abatement
  • Operational and load testing (125% of design load)
  • Provided training for equipment operation to the government officials